Distribution Center Metal Roof Upgrade

Standing-seam panels installed in phases so a busy warehouse never closed a loading bay.

Commercial

Distribution Center Metal Roof Upgrade

Standing-seam panels installed in phases so a busy warehouse never closed a loading bay.

Commercial

Distribution Center Metal Roof Upgrade

Standing-seam panels installed in phases so a busy warehouse never closed a loading bay.

Location

Fort Worth, TX

Property

Distribution warehouse

Roof area

38,000 sq ft

Material

Standing-seam metal

Duration

5 weeks

Completed

February 2026

The brief

A leaking roof over a warehouse that could not close.

An aging metal roof was letting water into the packing area during every heavy storm. The client needed a long-term fix without slowing down shipping.

Rusted fasteners, failed seams above the packing hall, and no room for a shutdown during peak season.

Job sheet

Property

Distribution warehouse

Crew

Commercial crew · 12 roofers

Roof area

38,000 sq ft

Completed

February 2026

Warranty

20-year system

What we found

The inspection, in plain words.

Every finding came with photos and a clear rating, so the owners knew what had to be done now and what could wait.

Finding 01

Replace

Failed seams over the packing hall

Open laps and rusted fasteners were letting water onto the packing lines during every heavy storm.

Finding 02

Repair

Gutters and downspouts undersized

Overflowing gutters were pushing water back under the panel edges along the loading side.

Finding 03

Watch

Skylight curbs near end of life

Still sound for now. Added to the maintenance plan for a check after each storm season.

Replace: worn out across the area · Repair: one fault letting water in · Watch: fine for now, checked again next year

Scope of work

What the price covered.

Moisture survey and leak map of the full roof

Standing-seam panels installed in overnight sections

New insulation over the packing hall

Larger gutters and downspouts on the loading side

Two-year maintenance plan with post-storm checks

Project investment

$448,000

Fixed price across five phases, each signed off before the next began.

Changed on site

One extra night shift to stay ahead of a storm front, covered under the original price.

Build log

Day by day on site.

We mapped every leak with a moisture survey, then replaced the roof in overnight sections. Each section was sealed and water-tested before the morning shift arrived.

01

Week 1

Survey and staging

Moisture survey, leak map and a phase plan agreed with the warehouse manager.

02

Weeks 2–3

Packing hall section

Worst area first, replaced overnight so the shipping floor stayed open by day.

03

Week 4

Remaining roof and gutters

The rest of the roof in sections, with new gutters along the loading docks.

04

Week 5

Final inspection and handover

Water test, punch list closed and the maintenance schedule handed to the facilities team.

The result

How it turned out.

No shipping days lost, no leaks through the following storm season, and a maintenance plan the facilities team can budget around.

Finished

February 2026

We never lost a shipping day. They worked nights, kept the floor dry and sent a progress report every morning.

Facilities manager, Fort Worth

0 days

Of shipping lost during the five-week build

38,000

Square feet re-roofed in overnight sections

20 yr

Manufacturer system warranty on the new roof

Your roof. Our responsibility.

Ready to protect your home?

Book a free roof inspection and get a clear, itemized estimate from licensed roofing professionals.

Your roof. Our responsibility.

Ready to protect your home?

Book a free roof inspection and get a clear, itemized estimate from licensed roofing professionals.

Your roof. Our responsibility.

Ready to protect your home?

Book a free roof inspection and get a clear, itemized estimate from licensed roofing professionals.

Trofo
Loading00

Create a free website with Framer, the website builder loved by startups, designers and agencies.